Multiple Choice

An electrical contractor reviews a completed commercial project and finds that the material costs were 12% higher than the original estimate, resulting in a net loss. The project data reveals the following timeline:

  • June: Estimate submitted using current copper prices.
  • July: Fixed-price contract signed without a price escalation clause.
  • August: A global copper market spike occurs (20% increase).
  • September: Materials purchased for the project.

The contractor attempted to use a different brand of wire in September to save costs, but the project engineer denied the request. When analyzing the project's financial failure, which factor represents the root cause of the unmanaged risk?

0

1

Updated 2026-05-08

Contributors are:

Who are from:

Tags

Electrician Business Operations

Running an Electrical Contracting Business Course

Related