Sequence Ordering

You won a bid for a commercial project three months ago, but the start date was delayed. Now that you are ready to order materials, the price of the specified steel conduit has increased by 40%, threatening your profit margin. Arrange the steps you should take to apply a formal substitution procedure to manage this price volatility before purchasing materials.