Multiple Choice

An electrical contractor reviews the final numbers for a residential lighting project to understand why it was less profitable than expected. The records show:

  • Material Budget for the Job: $5,000
  • Total Materials Purchased: $6,500
  • Materials Returned to the Supplier: $1,200
  • Restocking Fee (25%): $300
  • Cash Refund Received: $900

Which of the following is the most accurate analysis of how these material decisions affected the project's bottom line?