Multiple Choice

Review the timing of retainage in a long construction job. An electrical contractor is on an 8-month data-center retrofit. The owner withholds 15% retainage, and the subcontractor finishes its portion in Month 1. Under a retainage flow-down practice, the contractor does not expect to collect that portion from the owner until Month 8.

Which management strategy most effectively limits the firm's cash-flow risk while still communicating professionally with the subcontractor?