Multiple Choice

Your electrical contracting firm is the prime contractor for a new retail build-out scheduled to take 8 months. The client is withholding 10% retainage from your monthly payments. You hire a subcontractor to handle the low-voltage wiring for a total of $20,000, and they complete their entire scope of work by the end of Month 2. Following the practice of 'retainage flow-down,' which of the following actions represents the correct way to handle their final invoice?