Sequence Ordering

You are the primary electrical contractor on a large commercial build. The project owner is holding a 5% retainage on your contract until the building is completely finished in month 9. You hire a specialized trenching subcontractor who will complete all their underground work by month 2. To properly apply the 'flow-down' practice while maintaining a good relationship, arrange your management actions in the correct chronological order.