Fill in the Blank

Upon evaluating a rejected change order for unexpected underground water encountered during conduit trenching, an electrical contractor realizes the owner's rejection is valid because the original bid package included no soil reports to contradict. To successfully defend an appeal, the contractor must pivot their strategy and evaluate historical local data to prove the water level is of an unusual nature and not ordinarily found in that area, legally justifying the appeal as a Type ____ differin