Multiple Choice

Watch the provided video segment. You are drafting a formal notification letter to the general contractor after your electrical crew hits an unmarked, buried concrete vault while trenching for underground conduit. The project's geotechnical report, which was included in your contract documents, explicitly labeled this exact area as 'unobstructed native soil.' To formulate the most accurate Differing Site Condition claim, which argument structure MUST you synthesize into your letter?