Your electrical company is trenching for an underground conduit run in a commercial parking lot. The project's geotechnical report, which was included in your contract documents, states the excavation area consists of 'loose silty soil.' However, at a depth of 33 feet, your crew hits a solid, continuous layer of granite that will require an additional $$5,200$$ in specialized equipment rentals to remove. Based on the definitions provided in the video, how should you categorize this claim in your notice to the project owner?