Multiple Choice

You are designing the Schedule of Values (the itemized list of task prices used for monthly billing) for a new $500,000 project. Your projections show that you will spend $55,000 in Month 1 on labor and materials, but the 10% retainage and 30-day payment delay will create a funding hole in your reserves. Which creative billing structure would you develop to ensure your first payment is large enough to cover these initial costs?