Multiple Choice

An electrical contractor completes $60,000 of work in the first month of a project, incurring $55,000 in costs. The contract specifies monthly progress billing, 10% retainage, and 30-day payment terms. Why does the contractor experience a temporary cash flow deficit during this period despite the work being profitable?