You are finishing a $5,000 electrical contract for a homeowner's new workshop. The homeowner has already moved in their workbenches and tools, and you have labeled all the panels. However, the local inspector failed the final inspection because two circuits were not properly grounded. You want to formally declare 'substantial completion' to start the warranty period and trigger the release of your retainage. Why is this milestone not yet reached in this scenario?