Fill in the Blank

Your crew has energized all circuits, labeled the panels, and passed the final electrical inspection for a new office building. The owner can now occupy the space, even though you still need to return next week to replace a few scratched switch covers. At this point, to shift the responsibility for utilities to the owner, begin the warranty period, and initiate the release of your retainage, you must formally document that the project has reached ______________.