A commercial electrical project is 68% complete. The contract says retainage should drop from 8% to 4% once the job passes 60% completion, but the team never submitted that request. The project manager says it is too late now and the company should simply wait for final payment. Based on the cash-flow issue this creates, which evaluation is most accurate?