Multiple Choice

You are running an electrical project where retainage drops from 12% to 6% once the job reaches 60% completion. Your billing assistant suggests not submitting the formal request for the reduction because the project is on schedule and the paperwork seems minor. Based on sound cash flow practice, how should you evaluate that advice?