As an electrical contractor, you are evaluating why your company's cash flow is unnecessarily tight. You review a project that is 70% complete and notice the owner is still withholding 10% retainage, even though the contract allows it to drop to 5% after the halfway mark. You determine that your billing coordinator made a critical error by relying on the owner to automatically adjust the rate. To fix this process, you mandate that your team must proactively track this milestone and formally request the rate reduction in ____ to ensure the cash is unlocked.