An architect issues a field instruction for an AIA-style 'minor change in the work' to shift three light switches to the opposite side of a door frame to better suit a new furniture layout. During your site analysis, you find that the wall has already been finished with drywall and paint. Why does this discovery create a conflict with the 'minor change' classification?