True/False

Under AIA contract terms, if an architect verbally instructs your electrical crew to run an additional dedicated circuit to a new outlet location—requiring extra wire, a breaker, and two more hours of labor—this still qualifies as a 'minor change in the work' as long as the change is consistent with the overall intent of the contract documents.