You must evaluate an architect's directive that adds 20 feet of trenching for an underground feeder, which the architect has labeled an AIA-style 'minor change in the work.' Because you calculate this detour will require extra labor hours and equipment rental, you must reject the 'minor change' classification. To justify your refusal, you cite the contractual rule that a minor change cannot involve an adjustment to the contract time or the contract ____.