An architect issues a field instruction labeled as an AIA-style 'minor change in the work,' requiring your electrical team to swap 20 standard duplex receptacles for USB-integrated receptacles in a commercial lobby. The architect argues that because the installation labor time is identical for both types, the project budget and schedule are unaffected, making it a valid minor change. Based on the criteria for a minor change, how should you evaluate the architect's claim?