Multiple Choice

An electrical contractor is analyzing a contract that states: 'Retainage shall be released within 30 days of the completion of the project punch list.' To minimize the risk of payment delays, the contractor wants to negotiate this clause. Which of the following statements correctly analyzes why this specific trigger is problematic for a subcontractor?