Multiple Choice

An electrical contractor is attempting to collect payment for a $1,500 circuit upgrade requested by a homeowner during a kitchen renovation. The contractor has a text message from the homeowner saying, 'Sounds good, get it done,' but the original signed contract specifically states that 'all modifications to scope and price must be made via a signed Change Order form.' In a payment dispute, how would you evaluate the contractor's legal standing?

0

1

Updated 2026-05-09

Contributors are:

Who are from:

Tags

Electrician Business Operations

Running an Electrical Contracting Business Course

Related