Fill in the Blank

You are auditing a completed electrical project that went significantly over budget. The project manager defends the cost overruns by stating they completed several extra wiring upgrades requested verbally by the client on-site to keep the project moving. You evaluate the manager's decision as a critical failure because proceeding without written authorization leaves the contracting company without legally enforceable ________ that the client actually agreed to the new scope and higher price.