Fill in the Blank

An electrical contractor is drafting an agreement for a commercial service upgrade that requires a $12,000 custom transformer. The supplier demands full payment upon order placement, with an 8-week lead time. To prevent their own working capital from being tied up to finance the client's equipment, the contractor should require the client to pay a separate ____ aligned with these supplier terms before the order is placed.