Sequence Ordering

An electrical contractor is evaluating how to structure the deposit for a $100,000 commercial service upgrade that includes a $60,000 custom transformer. The supplier demands full payment for the transformer upfront before beginning the 12-week manufacturing process. Evaluate the following payment structures and arrange them in order from the highest financial risk to the contractor's working capital (first) to the lowest financial risk (last).