True/False

Suppose an electrical contractor quotes a project where specialized switchgear costs $15,000 but the contractor only collects a standard 10% mobilization deposit on a $20,000 total project price. If the supplier requires payment in full when the order is placed, the contractor is effectively financing the customer's equipment purchase because the upfront material cost exceeds the deposit collected.

0

1

Updated 2026-05-16

Contributors are:

Who are from:

Tags

Electrician Business Operations