Sequence Ordering

An electrical contractor reviews the monthly job-cost reports and notices that 'Job A' (a commercial retail fit-out) has an unexpected $800 budget overrun in materials, while 'Job B' (a residential service upgrade) has an unexpected $800 material surplus. Investigation reveals that technicians informally moved surplus conduit from 'Job A' directly to 'Job B' without documentation. To analyze and correct this discrepancy to ensure both projects reflect their true job costs, what is the correct sequence of steps the contractor must perform?