Multiple Choice

An electrical contractor's Application for Payment for a 'Service Panel Installation' line item includes the following details:

  • Cumulative Work to Date: $25,000
  • Prior Payments Received: $18,000
  • Retainage (10%): $2,500

If the 10% retainage rate has been applied consistently to all work since the project began, what is the specific value that must be listed for 'Work Completed this Period' to ensure the line item is mathematically consistent?