Multiple Choice

Two electrical contractors submit their monthly pay applications for a 'Lighting Fixture Installation' line item on their Schedule of Values.

  • Contractor A includes all five standard elements: (1) work this period, (2) cumulative work to date, (3) materials stored on site, (4) retainage, and (5) prior payments.
  • Contractor B provides a simplified breakdown showing only (1) work completed this period and (2) the remaining balance.

Evaluate which approach is more effective for ensuring