Fill in the Blank

You are analyzing why your electrical contracting company's pay applications are frequently delayed by general contractors. You discover your team is submitting simplified invoices that only show 'work completed this period' and the 'balance due'. You evaluate this practice as unacceptable and mandate the use of the standard five-element structure for every Schedule-of-Values line. You justify this strict policy to your team by explaining that providing the complete breakdown—including cumulative work, retainage, and prior payments—allows the GC to verify that your billed amounts accurately match the observed ________ on the job site, completely eliminating their need to delay payment to request supplemental documentation.