Multiple Choice

An electrical estimator is preparing a bid for a home renovation. They have listed 500 feet of electrical cable as a single takeoff line item. However, 400 feet are being installed in open framing for a new addition, while 100 feet must be 'fished' through existing finished walls in a kitchen. The estimator argues that because the material is the same, splitting the item is unnecessary. How should you evaluate this argument based on the principle of matching quantities to cost items?