Multiple Choice

You are designing the takeoff structure for a new park lighting project. The blueprints specify the following requirements:

• 15 Area Lights (Standard 10ft poles) • 5 Area Lights (Same fixture, but on 25ft decorative poles) • 1,000 feet of 1-inch PVC conduit • 800 feet is in a standard machine-dug trench • 200 feet must be hand-dug around protected tree roots

To ensure your bid accounts for all distinct labor and material costs, which organizational design should you create for your 'Lighting' and 'Conduit' takeoff sections?