Fill in the Blank

You are auditing a project estimate and must evaluate a junior estimator's work. They grouped 50 identical light fixtures into a single takeoff count, even though 10 fixtures are mounted on high exterior poles requiring a boom lift, and 40 are simple interior ceiling installations. You determine the estimate is flawed because the labor and equipment costs will differ significantly. To correct this error and ensure accurate pricing, you instruct the estimator to ________ the quantities based on their distinct installation conditions.