Multiple Choice

An estimator calculates that a project requires exactly 80 hours (two work weeks) of using an aerial lift. The overall project spans three months, with 40 lift hours scheduled in week 1 and the remaining 40 hours scheduled in week 12. In this context, how does performing an "electrical plant balance" help the estimator?