Multiple Choice

You are performing a plant balance review for an electrical project that spans 12 months. Your estimate shows a boom lift is required for high-bay rough-in in Month 2 and for final device trim-out in Month 11. Your financial analysis shows that returning the lift during the 8-month gap would save $3,000 in rent. However, your analysis of the building schedule reveals that the only large equipment access point will be permanently closed and replaced with a standard pedestrian door in Month 5.

Which conclusion must you draw by analyzing the relationship between these two facts?