Multiple Choice

You are the owner of an electrical contracting business bidding on a project where a scissor lift is required for high-bay conduit rough-in during Month 1 and lighting trim-out during Month 10. Your 'plant balance' review reveals that neither paying for 10 months of continuous rent nor paying for two separate mobilization fees will fit within your estimated equipment budget.

Which of the following actions represents the most effective creation of an original operational strategy to solve this plant balance conflict?