Fill in the Blank

As an electrical contractor reviewing a bid for a three-month project, you discover the estimator calculated the aerial lift cost by simply multiplying 80 total task hours by the rental rate. Since the lift is only required during the first and last weeks of the project, you must reject this approach. To perform a proper plant balance and find the true lowest cost, you must evaluate whether it is cheaper to pay rent while the lift sits idle on site for two months, or to return the lift and pay for a second ____.