Multiple Choice

As the business owner, you are designing a custom payment schedule for a new $200,000 electrical project. Your estimate shows that you will need $3,000 for permits, $30,000 for a non-refundable switchgear order, and $7,000 for initial materials before you can send your first monthly invoice. Which of these created plans successfully eliminates the 'mobilization cost gap'?