Fill in the Blank

You secure a $100,000 electrical project. Your actual upfront costs for permits, switchgear orders, and tool staging total 18% of the contract value. If you accept a standard 10% deposit from the customer, you will have to finance a $____ mobilization gap out of your own operating cash.