Multiple Choice

Examine the 'Actual vs. Estimate' report provided in the image. On the 'Finish / Plate' task, your crew recorded 24.50 total hours, while the original estimate was 16.00 hours. The report also highlights that this specific project incurred 5.00 hours for 'Material Pick-up' and 4.50 hours for 'Waiting for other trades.' By breaking down the relationship between the productive installation work and these non-productive logs, which conclusion most accurately identifies the root cause of the labor overrun?