Multiple Choice

Review the 'Actual vs. Estimate' report provided in the image. After seeing the 'Finish / Plate' task go 8.5 hours over budget, your foreman recommends that you permanently update your estimating software to use 25 hours for this task in all future bids to ensure you never lose money on it again.

Evaluate the strategic validity of the foreman's recommendation based on the data provided for 'Material Pick-up' and 'Waiting for other trades.'