You are designing a 'Cost-Protection Protocol' for your new electrical business to ensure that the material prices you use in your bids are the same prices you pay during construction. Based on the need to avoid the 'Actual vs. Estimate' cost overruns shown in the image, which set of requirements should you mandate for every major material line item in your estimating system?