Fill in the Blank

You are evaluating why a recent bid was rejected by a client despite having a competitive total price. The client noted they could not verify if permits, mobilization, and testing were included. You determine the proposal's critical failure was the lack of a detailed ________, which was needed to organize the overall scope into distinct cost buckets and communicate exactly what was being priced.