Multiple Choice

You have just finished clarifying the scope for a small commercial electrical project. The agreed-upon work includes: coordinating underground conduit runs with the site excavation contractor, installing a new 200-amp main panel, running branch circuits to all receptacles, hanging and wiring forty LED light fixtures, pulling the required electrical permit, and performing a final energization test before the inspector arrives. You are now designing the pricing schedule you will present to the client so that every dollar of cost is captured and the client can see exactly what they are paying for. Which set of cost buckets would produce the most complete and clearly communicated pricing schedule for this project?