Multiple Choice

A general contractor’s auditor flags an electrical subcontractor’s payment application for 'inflated progress' because the 'Branch Wiring' line item is reported at 110% completion. The subcontractor explains that the extra 10% is for an approved change order that was added to the original line item. Analyzing the auditor's perspective, why did this billing structure lead to a dispute?