Separate Base Scope and Change Orders on Each Payment Application

List approved change-order work on its own line items in the Application for Payment instead of folding it into the original contract amounts. That makes the submission easier to audit, shows exactly what belongs to the base scope versus the extra work, and reduces arguments about overstated completion percentages. Never bill for a change order that has not been approved yet. Keeping the records separate also supports clean closeout calculations and retainage release.