Sequence Ordering

As a project manager analyzing a disputed progress payment, you must trace a discrepancy back to its source using the Schedule of Values (SOV) framework. Arrange the following investigative steps in the logical order required to prove that a subcontractor overbilled for a 'Lighting Fixtures' line item this period.