True/False

When evaluating a subcontractor's progress billing invoice, a project manager should approve the payment request as long as the overall total amount billed is accurate, even if the invoice combines distinct phases like 'Rough-In' and 'Finish Materials' instead of mirroring the approved Schedule of Values.