Multiple Choice

You are designing the Schedule of Values (SOV) for a $150,000 warehouse project. You must pay $50,000 for a main switchboard in Month 2, but it will not be fully installed or energized until Month 6. To create a billing framework that protects your company's cash flow while providing a transparent 'math trail' for the general contractor, which design strategy is most effective?