Multiple Choice

You are submitting a progress billing for a commercial warehouse project. On your Schedule of Values (SOV), the 'High-Bay Lighting' line item has a total scheduled value of $10,000. You have the following information for this billing period:

  • Amount billed in all previous months: $4,000
  • Value of labor and materials installed this month: $3,000
  • Value of light fixtures delivered and stored on-site (not yet installed): $2,000

Based on the SOV billing framework, what is the correct 'Total Completed and Stored to Date' to enter for this line item?